Deployment tool 0957A-34100A
Before scrapping any airbags or side airbags (including those
in a whole vehicle to be scrapped), the airbags or side airbags must be
deployed. If the vehicle is still within the warranty period, before
deploying the airbags or side airbags, the Technical Manager must give
approval and/or special instruction. Only after the airbags or side
airbags have been deployed (as the result of vehicle collision, for
example), can they be scrapped. If the airbags or side airbags appear
intact (not deployed), treat them with extreme caution. Follow this
procedure.
Deploying Airbags In The Vehicle
If an SRS equipped vehicle is to be entirely scrapped, its
airbags or side airbags should be deployed while still in the vehicle.
The airbags or side airbags should not be considered as salvageable
parts and should never be installed in another vehicle.
1. |
Turn the ignition switch OFF, and disconnect the battery negative cable and wait at least three minutes. |
2. |
Confirm that each airbag or side airbag is securely mounted. |
3. |
Confirm that the special tool is functioning properly by following the check procedure.
(1) |
Driver’s Airbag :
–
|
Remove the driver’s airbag and install the SST (0957A-38510). |
–
|
Install the driver’s airbag on the steering wheel. |
|
(2) |
Front Passenger’s Airbag :
–
|
Remove the glove box housing, and then disconnect the connector between the front passenger’s airbag and SRS main harness. |
–
|
Install the SST(0957A-3Q100). |
|
(3) |
Side Airbag :
–
|
Disconnect the 2P connector between the side airbag and wire harness. |
–
|
Install the SST (0957A-3F100). |
|
(4) |
Curtain Airbag :
–
|
Disconnect the 2P connector between the curtain airbag and wire harness. |
–
|
Install the SST (0957A-3S100). |
|
(5) |
Seat Belt Pretensioner :
–
|
Disconnect the 2P connector from the seat belt pretensioner. |
–
|
Install the SST (0957A-38500). |
|
(6) |
Anchor Pretensioner :
–
|
Disconnect the 2P connector from the anchor pretensioner. |
–
|
Install the SST (0957A-38500). |
|
|
4. |
Place the deployment tool at least thirty feet (10meters) away from the airbag. |
5. |
Connect a 12 volt battery to the tool. |
6. |
Push the tool’s deployment switch. The airbag should deploy
(deployment is both highly audible and visible: a loud noise and rapid
inflation of the bag, followed by slow deflation) |
7. |
Dispose of the complete airbag. No parts can be reused. Place it in a sturdy plastic bag and seal it securely.
|
Deploying the airbag out of the vehicle
If an intact airbag has been removed from a scrapped vehicle,
or has been found defective or damage during transit, storage or
service, it should be deployed as follows:
1. |
Confirm that the special tool is functioning properly by following the check procedure on this page. |
2. |
Position the airbag facing up and EFD (Emergency Fastening
Device) and Active Hood Actuator must be placed in piled up, at least, 5
tires, outdoors on flat ground at least thirty feet (10meters) from any
obstacles or people. |
3. |
Connect a 12 volt battery to the tool. |
4. |
Push the tool’s deployment switch. The airbag should deploy
(deployment is both highly audible and visible: a loud noise and rapid
inflation of the bag, followed by slow deflation) |
5. |
Dispose of the complete airbag. No parts can be reused. Place it in a sturdy plastic bag and seal it securely.
|
–
|
When EFD and Active Hood Actuator are deployed, broken parts are exploded and scattered. |
–
|
EFD and Active Hood Actuator must be placed in the piled up 5 tires to avoid exploded broken parts. |
–
|
Technicians should wear an eye protector and extremely be cautions of exploded broken parts.
|
|
Disposal of Damaged Airbag
1. |
If installed in a vehicle, follow the removal procedure of driver’s airbag front passenger’s and side airbag. |
2. |
In all cases, make a short circuit by twisting together the two airbag inflator wires. |
3. |
Package the airbag in exactly the same packing that the new replacement part come in. |
Removal
1.
Disconnect the battery negative cable and wait for at least thirty seconds before beginning work.
2.
Remove the roof trim. (Refer to the Body group- Interior)
3.
Disconnect the ...